2022-0068-PR2022-0074 Furnishing of Labor, Materials and Equipment for the Concreting of Jct. (TER) Canayaon – Roxas – Tabuan – Datag Rd., Garcia Hernandez, Bohol, by the Provincial Engineer’s Office,
Approved Budget:
Php2,491,042.11
Procurement Mode:
Public Bidding
Classification:
Civil Works
Category:
Construction Projects
Applicable Procurement Rules:
Implementing Rules and Regulations
Funding Source:
Government of the Philippines (GOP)
Funding Instrument:
Budget for the Contract Approved by the Sanggunian
Location:
Bohol
Contract Duration:
45 Day/s
PROVINCE OF BOHOLNew Capitol Complex, Tagbilaran City Bohol, Region VII, PhilippinesFurnishing of Labor, Materials and EquipmentAwardee :Contact Person :3N CONSTRUCTION & SUPPLYManuelito Relampagos MosquedaAddress :Designation :Sta. Cruz, Calape Bohol, Region VII, PhilippinesProprietor

Line Item#Product/Service/Project NameBudget1Furnishing of Labor, Materials and Equipment, for the Concreting of Jct. (TER) Canayaon – Roxas – Tabuan – Datag Rd., Garcia Hernandez, Bohol, 72141000, 1, LotPhp2,491,042.11

Reason for Award :Single Calculated and Responsive Bid
Award Type:
Award Notice
Contract Amount:
Php2,489,953.82
Award Date:
10-Mar-2023
Publish Date:
22-Mar-2023
Date Last Updated:
03-May-2023
Contract Number:
2023-162
Proceed Date:
12-Apr-2023
Contract Effectivity Date:
20-Apr-2023
Contract End Date:
21-Apr-2023
Date Created:
22-Mar-2023